DOTD officials said the bridge will fully close starting at 6 a.m. on Monday, July 14, until 6 p.m. on Friday, Aug. 8 for repairs to the bridges pedestal and pads.
They are the concrete areas supporting the bridge’s driving span while down for vehicle crossing.
Expansion joints will also be cleaned.
The work is due to the bridge not properly settling when returning from the upright position, according to the DOTD. They add that repair efforts were attempted without full bridge closure in the past.
DOTD officials say to fully resolve the issue, concrete must be repoured in certain areas and have time to cure before supporting vehicle weight.
The bridge previously closed for five days in May, due to mechanical repairs.
Lafayette contractor C.E.C., Inc will be performing the work.
Walmart bought Vizio in 2024, and now it's taking the next steps to formally fold…
TriZetto Provider Solutions, a healthcare technology subsidiary of the IT services giant Cognizant, has officially…
The woman at the door wore a plush lobster headdress. She sat in the front…
There are a lot of games that try to emulate The Legend of Zelda, but…
200 Years Ago Notice! Persons desirous of taking stock in the Hampshire and Hampden Canal…
As rural schools struggle to secure effective state support, school districts and officials in Franklin…
This website uses cookies.