Mississippi receives $32 million for Yazoo Backwater Area pumps

JACKSON, Miss. (WJTV) – U.S. Senator Cindy Hyde-Smith (R-Miss.) announced that the U.S. Army Corps of Engineers (USACE) is directing $136.5 million in FY2025 appropriations to Mississippi for work on 30 projects. This includes $32 million for mitigation requirements and pre-construction project planning for the new, recently approved Yazoo Backwater Area Water Management Project.

“I am very pleased with the Army Corps FY25 Work Plan funding, which will strengthen Mississippi’s levees, keep our ports and waterways operational, and support critical infrastructure improvements that are already underway,” Hyde-Smith said.

In addition to the Yazoo pumps funding, the FY2025 Work Plan provides $13 million for Arkabutla Lake, which will be used for commonly performed operation and maintenance work as well as for dam inspections, assessments, and dam safety interim risk reduction measures.

U.S. Army Corps of Engineers FY2025 Work Plan (Mississippi)

Investigations

  • Gulfport Harbor, MS – $1,250,000
  • TOTAL – $1,250,000

Mississippi River and Tributaries (MR&T)

MR&T Construction              

  • Yazoo Backwater Area – $32,000,000
  • TOTAL – $32,000,000

MR&T Operations and Maintenance

  • Greenville Harbor – $1,334,000
  • Inspection of Completed Works – $647,000
  • Vicksburg Harbor – $1,045,000
  • Arkabutla Lake – $13,062,000
  • Big Sunflower River – $350,000
  • Enid Lake – $6,023,000
  • Greenwood, MS – $1,223,000
  • Grenada Lake – $6,125,000
  • Main Stem, MS – $1,157,000
  • Sardis Lake – $6,834,000
  • Tributaries, MS – $841,000
  • Whittington Aux. Channel – $321,000
  • Yazoo Backwater Area – $1,010,000
  • Yazoo City, MS – $393,000
  • TOTAL – $40,365,000

Operation and Maintenance (O&M)

  • Tennessee-Tombigbee Waterway (wildlife mitigation) – $1,890,000
  • Tennessee-Tombigbee Waterway (O&M) – $34,251,000
  • East Fork, Tombigbee River – $305,000
  • Gulfport Harbor          – $11,270,000
  • Inspection of Completed Works         – $228,000
  • Okatibbee Lake – $1,948,000
  • Pascagoula Harbor – $10,602,000
  • Pearl River, MS and LA – $152,000
  • Project Condition Surveys – $173,000
  • Rosedale Harbor – $1,692,000
  • Water/Environmental Certification – $30,000
  • Yazoo River – $237,000
  • Claiborne County Port – $150,000
  • Mouth of Yazoo River – $37,000
  • TOTAL – $62,965,000
rssfeeds-admin

Recent Posts

Indie Horror Games Are Invading Hollywood, and They Have the Fans to Thank For It

Watching a streamer find their way through the digital labyrinth of some spooky game—particularly one…

48 minutes ago

GPT‑5.5 Bio Bug Bounty to Strengthen Advanced AI Capabilities

OpenAI has announced a new Bio Bug Bounty program for GPT-5.5 as part of its…

54 minutes ago

Bucks County NAACP Hosts ‘Black History and Democracy at Risk’ Town Hall

In the wake of the 2024 presidential election, communities across the country are still reeling…

59 minutes ago

Steel Ball Run Doesn’t Have A Theme Song Yet, JoJo’s Fans Made One Anyway

Though we’ve previously reported that the anime adaptation of JoJo’s Bizarre Adventure: Steel Ball Run…

2 hours ago

A Look Back, April 25

200 Years Ago John Clarke, directly opposite the Meeting House in Northampton, has on hand…

2 hours ago

Man hospitalized after car crash in Leverett

LEVERETT — A middle-aged man was transported to Baystate Medical Center in Springfield with “moderate-to-severe”…

2 hours ago

This website uses cookies.